File #: 24-2329   
Placement: Purchase Order/Bid Items Status: Passed
File created: 5/24/2024 In control: School Board Regular Meeting
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Award Bid #23052-00, Roof Replacement & Designated Repairs for Nature Coast Technical High School, to Advanced Roofing, Inc., and approve the contract and the purchase of construction goods and services for $1,916,739.00.
Attachments: 1. 24-2329 Advertisement for Bids.pdf, 2. 24-2329 Advanced Roofing Bid Submittal.pdf, 3. 24-2329 Bid Tab for bid opening 23052.00.pdf, 4. 24-2329 Letter of Recommendation - NCTHS Phase1.pdf, 5. 24-2329 A101-2017 GC Agreement Signed.pdf, 6. 24-2329 A101-2017 Exhibit A.pdf, 7. 24-2329 A201-2017 General Conditions.pdf, 8. 24-2329 Exhibit D - Standard Addendum to Agreements.pdf, 9. 24-2329 Exhibit E - Conflict of Interest.pdf, 10. 24-2329 Budget Sheet- NCTHS Roof Replacement.pdf, 11. Exhibit C 24-2329 062524

Title and Board Action Requested

title

Award Bid #23052-00, Roof Replacement & Designated Repairs for Nature Coast Technical High School, to Advanced Roofing, Inc., and approve the contract and the purchase of construction goods and services for $1,916,739.00.

 

body

Executive Summary

The Director of Facilities & Construction, on behalf of the Superintendent of Schools, hereby requests the Board award Bid #23052-00, Roof Replacement & Designated Repairs for Nature Coast Technical High School, to Advanced Roofing, Inc., and approve the contract and the purchase of construction goods and services for $1,916,739.00.

 

My Contact

Brian Ragan

Director of Facilities & Construction

ragan_b@hcsb.k12.fl.us

352-797-7050

 

2023-28 Strategic Focus Area

Priority 3: Safe and Healthy Learning Environment

 

Financial Impact

See attached budget sheet.

 

If expenditure is not currently budgeted, this will serve as the budget amendment when Board approved. If the agenda item includes the purchase of goods or services, the funds requested are an anticipated amount and may fluctuate depending on such factors as current market conditions, product availability, additional funding sources, and the needs of the District.  Should the actual cost exceed the anticipated amount, the Board approves the additional cost, after review by the superintendent, but not in excess of the funds available in the site’s approved annual budget.