On agenda: 6/27/2023 Final action: 6/27/2023
Title: Approve the agreement and authorize the purchase of pre-construction services for the Brooksville Elementary School Phase 2 HVAC Project, from JE Dunn, for an estimated budget of $1,200,000.00, which includes the purchase of $12,000.00 in pre-construction services.
Attachments: 1. 23-1494 CM Agreement Signed by JE Dunn, 2. 23-1494 Budget Sheet

Title and Board Action Requested

title

Approve the agreement and authorize the purchase of pre-construction services for the Brooksville Elementary School Phase 2 HVAC Project, from JE Dunn, for an estimated budget of $1,200,000.00, which includes the purchase of $12,000.00 in pre-construction services.

 

body

Executive Summary

The Director of Facilities and Construction, on behalf of the Superintendent of Schools, hereby requests the Board approve the agreement and authorize the purchase of pre-construction services for the  Brooksville Elementary School Phase 2 HVAC Project, from JE Dunn, for an estimated budget of $1,200,000.00, which includes the purchase of $12,000.00 in pre-construction services.

 

The construction cost for this project is estimated to be $1,200,000.00.  Upon completion of Pre-construction Phase services, this Agreement will be modified by a Guaranteed Maximum Price Amendment to establish the total Cost of the Work.

 

My Contact

Brian Ragan

Director of Facilities & Construction

ragan_b@hcsb.k12.fl.us

(352) 797-7050

 

2018-23 Strategic Focus Area

Pillar 3: Facility Operations

 

Financial Impact

See attached budget sheet.