File #: 26-3217   
Placement: All Other Support Operations Agenda Items Status: Agenda Ready
File created: 8/7/2025 In control: School Board Regular Meeting
On agenda: 9/9/2025 Final action:
Title: Approve the Final Acceptance/Closeout to the agreement with The A. D. Morgan Corporation for Construction Manager Services for the New Air Rifle Range for Central High School ROTC using donated funds.
Attachments: 1. 26-3217 AIA_G704_Cert of Substantial Completion, 2. 26-3217 OEF 209 Cert of Final Inspection, 3. 26-3217 AIA G701-2017 Final Change Order, 4. 26-3217 PAY APP #11 Final Payment, 5. 26-3217 Final Release of Lien, 6. 26-3217 Budget Sheet NO Financial Impact
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title and Board Action Requested

title

Approve the Final Acceptance/Closeout to the agreement with The A. D. Morgan Corporation for Construction Manager Services for the New Air Rifle Range for Central High School ROTC using donated funds.

 

body

Executive Summary

The Director of Facilities & Construction, on behalf of the Superintendent of Schools, hereby requests the Board approve the final acceptance/closeout to the agreement with The A. D. Morgan Corporation for Construction Manager Services for the New Air Rifle Range for Central High School ROTC using donated funds.

 

The original contract amount was $1,190,061.00, of which $1,011,585.54 has been paid, leaving a balance of $178,475.46. Change order 01.1 reduces the contract by $178,475.46 leaving a balance of $0.00.

 

My Contact

Brian Ragan

Director of Facilities & Construction

ragan_b@hcsb.k12.fl.us

352-797-7050

 

2023-28 Strategic Focus Area

Priority 5: Fiscal Transparency and Capital Planning

 

Financial Impact

See attached budget sheet.

 

If expenditure is not currently budgeted, this will serve as the budget amendment when Board approved. If the agenda item includes the purchase of goods or services, the funds requested are an anticipated amount and may fluctuate depending on such factors as current market conditions, product availability, additional funding sources, and the needs of the District.  Should the actual cost exceed the anticipated amount, the Board approves the additional cost, after review by the superintendent, but not in excess of the funds available in the site’s approved annual budget.