Skip to main content
Hernando Schools Banner
File #: 23-1499   
Placement: Purchase Order/Bid Items Status: Agenda Ready
File created: 6/2/2023 In control: School Board Regular Meeting
On agenda: 6/27/2023 Final action:
Title: Approve the agreement and authorize the purchase of pre-construction services for the Winding Waters K8 Restroom Project, from Walbridge Aldinger, LLC, for an estimated budget of $525,000.00, which includes the purchase of $5,250.00 in pre-construction services.
Attachments: 1. 23-1499 Agreement, 2. 23-1499 Budget Sheet
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title and Board Action Requested

title

Approve the agreement and authorize the purchase of pre-construction services for the Winding Waters K8 Restroom Project, from Walbridge Aldinger, LLC, for an estimated budget of $525,000.00, which includes the purchase of $5,250.00 in pre-construction services.

 

body

Executive Summary

The Director of Facilities and Construction, on behalf of the Superintendent of Schools, hereby requests the Board approve the agreement and authorize the purchase of pre-construction services for the Winding Waters K8 Restroom Project, from Walbridge Aldinger, LLC, for an estimated budget of $525,000.00, which includes the purchase of $5,250.00 in pre-construction services.

 

The construction cost for this project is estimated to be $525,000,00.  Upon completion of Pre-construction Phase services, this Agreement will be modified by a Guaranteed Maximum Price Amendment to establish the total Cost of the Work.

 

My Contact

Brian Ragan

Director of Facilities & Construction

ragan_b@hcsb.k12.fl.us

(352) 797-7050

 

2018-23 Strategic Focus Area

Pillar 3: Facility Operations

 

Financial Impact

See attached budget sheet.