File #: 25-2774   
Placement: Purchase Order/Bid Items Status: Passed
File created: 12/20/2024 In control: School Board Regular Meeting
On agenda: 1/14/2025 Final action: 1/14/2025
Title: Approve the Amendment to the Agreement with J. E. Dunn Construction Co., for construction goods and services for the 30 Classroom Addition for Winding Waters K-8 School and authorize the purchase of construction goods and services for $2,653,870.00.
Attachments: 1. 25-2774 Parital GMP Amendment Signed.pdf, 2. 25-2774 WWK8 WWHS Phase 1 GMP Summary.pdf, 3. 25-2774 Budget Sheet- WWK8 30 classroom addition Amendment.pdf
Related files: 25-2856

Title and Board Action Requested

title

Approve the Amendment to the Agreement with J. E. Dunn Construction Co., for construction goods and services for the 30 Classroom Addition for Winding Waters K-8 School and authorize the purchase of construction goods and services for $2,653,870.00.

 

body

Executive Summary

The Director of Facilities & Construction, on behalf of the Superintendent of Schools, hereby

requests the Board approve the Amendment to the Agreement with J. E. Dunn Construction Co., for construction goods and services for the 30 Classroom Addition for Winding Waters K-8 School and authorize the purchase of construction goods and services for $2,653,870.00.

 

This Partial GMP Amendment is being executed solely for the purchase of the project’s pre-cast panels. Due to the long procurement lead times and to maintain the project schedule, these items must be ordered prior to the final GMP amount being established. A forthcoming GMP Amendment will be executed for the remainder of the project.

 

My Contact

Brian Ragan

Director of Facilities & Construction

ragan_b@hcsb.k12.fl.us

352-797-7050

 

2023-28 Strategic Focus Area

Priority 5: Fiscal Transparency and Capital Planning

 

Financial Impact

See attached budget sheet.

 

If expenditure is not currently budgeted, this will serve as the budget amendment when Board approved. If the agenda item includes the purchase of goods or services, the funds requested are an anticipated amount and may fluctuate depending on such factors as current market conditions, product availability, additional funding sources, and the needs of the District.  Should the actual cost exceed the anticipated amount, the Board approves the additional cost, after review by the superintendent, but not in excess of the funds available in the site’s approved annual budget.