Skip to main content
Hernando Schools Banner
File #: 24-2341   
Placement: Purchase Order/Bid Items Status: Passed
File created: 5/28/2024 In control: School Board Regular Meeting
On agenda: 6/11/2024 Final action: 6/11/2024
Title: Approve the Closeout/Final Acceptance to the contract with Air Mechanical and Service Corp. for Suncoast Elementary School HVAC Renovation (Phase 2) and Authorize Final Payment in the Amount of $35,185.82.
Attachments: 1. 24-2341 Certificate of Final Completion.pdf, 2. 24-2341 Release of Lien.pdf, 3. 24-2341 Final Reconciling Change Order.pdf, 4. 24-2341 Notice of Final Acceptance.pdf, 5. 24-2341 Notice of Final Settelement.pdf, 6. 24-2341 Final Application for Payment.pdf, 7. 24-2341 Budget Sheet - SES Phase II Close Out r2.pdf

Title and Board Action Requested

title

Approve the Closeout/Final Acceptance to the contract with Air Mechanical and Service Corp. for Suncoast Elementary School HVAC Renovation (Phase 2) and Authorize Final Payment in the Amount of $35,185.82.

 

body

Executive Summary

The Director of Facilities and Construction, on behalf of the Superintendent of Schools, hereby requests the Board Approve the Closeout/Final Acceptance to the contract with Air Mechanical and Service Corp. for Suncoast Elementary School HVAC Renovation (Phase 2) and Authorize Final Payment in the Amount of $35,185.82.

 

The original contract sum was $3,642,951.00 of which $3,483,394.25 has been paid to date, leaving a balance of $159,556.75.  Change Order 01 returns to the School Board $124,370.93.  The final payment due to the Contractor, therefore, is $35,185.82.

 

My Contact

Brian Ragan

Director of Facilities & Construction

ragan_b@hcsb.k12.fl.us

352-797-7050

 

2023-28 Strategic Focus Area

Priority 3: Safe and Healthy Learning Environment

 

Financial Impact

See attached budget sheet.