Approve the Closeout/Final Acceptance to the contract with Air Mechanical and Service Corp. for Suncoast Elementary School HVAC Renovation (Phase 2) and Authorize Final Payment in the Amount of $35,185.82.
body
Executive Summary
The Director of Facilities and Construction, on behalf of the Superintendent of Schools, hereby requests the Board Approve the Closeout/Final Acceptance to the contract with Air Mechanical and Service Corp. for Suncoast Elementary School HVAC Renovation (Phase 2) and Authorize Final Payment in the Amount of $35,185.82.
The original contract sum was $3,642,951.00 of which $3,483,394.25 has been paid to date, leaving a balance of $159,556.75. Change Order 01 returns to the School Board $124,370.93. The final payment due to the Contractor, therefore, is $35,185.82.
My Contact
Brian Ragan
Director of Facilities & Construction
ragan_b@hcsb.k12.fl.us
352-797-7050
2023-28 Strategic Focus Area
Priority 3: Safe and Healthy Learning Environment
Financial Impact
See attached budget sheet.