Legislation Details

File #: 25-2781   
Placement: Purchase Order/Bid Items Status: Passed
File created: 1/7/2025 In control: School Board Regular Meeting
On agenda: 1/28/2025 Final action: 1/28/2025
Title: Award RFQ #9009-2408-0010, Continuing Engineering Services for Projects One Million Dollars or Less, to ASR Engineering, Inc., OCI Associates LLC dba CMTA, Coastal Design Consultants, Inc., DDC Engineering, Inc., Engineering Matrix, Inc., George F Young, Gulf Atlantic Engineers PA, KBA Engineering, Inc., Kimley-Horn & Associates, Inc., KPI Engineering, Inc., Long & Associates Architects/Engineers, Inc., McKim & Creed, Inc., MES Group, Inc., Phoenix Engineering Group, Inc., Raymond Engineering-Georgia, Inc., REI Engineers, Inc., and SGM Engineering, Inc., for consulting engineering services (Civil, Structural, Plumbing, Fire Protection, Mechanical, Electrical and Low Voltage Systems) for miscellaneous projects to be awarded on an ongoing basis, and authorize the purchase of said services for an estimated annual amount of $500,000.00.
Attachments: 1. 25-2781 RFQ Continuing Engineering 1 MIL or Less, 2. 25-2781 Score Sheets CS Engineers 1 MIL or Less Ranking By Discipline, 3. 25-2781 ASR C103-2015 with Attachments Signed, 4. 25-2781 CMTA C103-2015 with Attachments Signed, 5. 25-2781 Coastal C103-2015 with Attachments Signed, 6. 25-2781 DDC C103-2015 with Attachments Signed, 7. 25-2781 EngMatrix C103-2015 with Attachments Signed, 8. 25-2781 GF Young C103-2015 with Attachments Signed, 9. 25-2781 Gulf Atlantic C103-2015 with Attachments Signed, 10. 25-2781 KBA C103-2015 with Attachments Signed, 11. 25-2781 Kimley-Horne C103-2015 with Attachments Signed, 12. 25-2781 KPI C103-2015 with Attachments Signed, 13. 25-2781 Long&Associates C103-2015 with Attachments Signed, 14. 25-2781 McKim&Creed C103-2015 with Attachments Signed, 15. 25-2781 MES C103-2015 with Attachments Signed, 16. 25-2781 Phoenix C103-2015 with Attachments Signed, 17. 25-2781 Raymond C103-2015 with Attachments Signed, 18. 25-2781 REI C103-2015 with Attachments Signed, 19. 25-2781 SGM C103-2015 with Attachments Signed, 20. 25-2781 Budget Sheet Cont Eng Svcs Projects 1 MIL or Less

Title and Board Action Requested

title

Award RFQ #9009-2408-0010, Continuing Engineering Services for Projects One Million Dollars or Less, to ASR Engineering, Inc., OCI Associates LLC dba CMTA, Coastal Design Consultants, Inc., DDC Engineering, Inc., Engineering Matrix, Inc., George F Young, Gulf Atlantic Engineers PA, KBA Engineering, Inc., Kimley-Horn & Associates, Inc., KPI Engineering, Inc., Long & Associates Architects/Engineers, Inc., McKim & Creed, Inc., MES Group, Inc., Phoenix Engineering Group, Inc., Raymond Engineering-Georgia, Inc., REI Engineers, Inc., and SGM Engineering, Inc., for consulting engineering services (Civil, Structural, Plumbing, Fire Protection, Mechanical, Electrical and Low Voltage Systems) for miscellaneous projects to be awarded on an ongoing basis, and authorize the purchase of said services for an estimated annual amount of $500,000.00.

 

body

Executive Summary

The Director of Facilities & Construction, on behalf of the Superintendent of Schools, hereby requests the Board award RFQ #9009-2408-0010, Continuing Engineering Services for Projects One Million Dollars or Less, to ASR Engineering, Inc., OCI Associates LLC dba CMTA, Coastal Design Consultants, Inc., DDC Engineering, Inc., Engineering Matrix, Inc., George F Young, Gulf Atlantic Engineers PA, KBA Engineering, Inc., Kimley-Horn & Associates, Inc., KPI Engineering, Inc., Long & Associates Architects/Engineers, Inc., McKim & Creed, Inc., MES Group, Inc., Phoenix Engineering Group, Inc., Raymond Engineering-Georgia, Inc., REI Engineers, Inc., and SGM Engineering, Inc., for consulting engineering services (Civil, Structural, Plumbing, Fire Protection, Mechanical, Electrical and Low Voltage Systems) for miscellaneous projects to be awarded on an ongoing basis, and authorize the purchase of said services for an estimated annual amount of $500,000.00.

 

My Contact

Brian Ragan

Director of Facilities & Construction

ragan_b@hcsb.k12.fl.us

352-797-7050

 

2023-28 Strategic Focus Area

Priority 5: Fiscal Transparency and Capital Planning

 

Financial Impact

See attached budget sheet.

 

If expenditure is not currently budgeted, this will serve as the budget amendment when Board approved. If the agenda item includes the purchase of goods or services, the funds requested are an anticipated amount and may fluctuate depending on such factors as current market conditions, product availability, additional funding sources, and the needs of the District.  Should the actual cost exceed the anticipated amount, the Board approves the additional cost, after review by the superintendent, but not in excess of the funds available in the site’s approved annual budget.